The complete demolition of Frodsham Science and Technology College was carried out as principal contractors to Cheshire West and Chester Council. Our appointment formed part of an NEC 2 Strategic Framework Agreement and a multi million pound regeneration of the area to make way for the building of a new Health Care Centre.
The works included for:
- Asbestos removal
- Soft strip
- Demolition
- Crushing high volumes of demolition rubble
During the works we were faced with challenging interfaces around the site boundary including densely populated residential housing and an adjoining live leisure centre which remained open throughout. The project manager for the council was very happy with our commitment to safety and the environment.
A full detailed reference letter from the council is available upon request..